← The 2027 National BudgetLaging Pasulong

Budget oversight brief · FY2027 deliberations

Eleven years of National Government Data Center contracts

DICT reported 72 contract entries worth ₱4.98 billion for the National Government Data Center programme, FY2016–FY2026. Three quarters of that went to renting capacity from private providers — while the department was also building its own facilities. This brief reconstructs the ledger and sets out what the submission does not answer.

Source document
“List of NGDC Projects from FY 2016 to FY 2026”, 5 pp.
Transmitted by
DICT, 15 September 2026, per Committee on Appropriations directive of 7 September 2026
Addressee
Rep. Antonio L. Tinio, ACT Teachers Party-list
Amounts
Final contract value in PHP, as reported by DICT
Total contract value
₱4.98B
72 entries, FY2016–FY2026
Rented vs. built
75.2%
₱3.75B to cloud & colocation; ₱888M to government-owned facilities
Supplier concentration
82.4%
Share held by the top 10 of 33 suppliers
Renewals & extensions
24
One third of all entries; ₱722M

Where the money went

Annual contract value by type of spending. FY2023–FY2026 account for ₱3.50B — 70.3% of the eleven-year total — and FY2024 alone for 37.8%.

Contract value awarded per fiscal year

Stacked by category. Hover a segment for detail.

  • Cloud & managed services
  • Colocation & space/rack lease
  • Construction & facilities
  • Network, equipment, consultants, other

Findings

Nine observations that the ledger supports on its face. None is a conclusion about wrongdoing: the submission carries no approved budget for the contract, procurement modality, or bidder count, so pricing and competition cannot be assessed from it alone.

F1

Spending trebled in the last four years without a stated capacity plan

FY2016–FY2022 averaged ₱211M a year. FY2023 jumped to ₱1.02B and FY2024 to ₱1.88B — 20 separate contracts in FY2024, the most in any year. The four most recent years hold 70.3% of eleven years of spending.

The step change is driven by two things at once: cloud subscriptions (₱734.9M in FY2023, ₱809.4M in FY2024) and the Subic build (₱697.9M). The list gives no indication that these were sequenced against a single capacity plan.

F2

Colocation spending rose in the same years the government built its own data centers

DICT built NGDC3 (₱130.3M, FY2017), added electrical and backup power (₱45.6M, FY2021) and developed the Subic site (₱697.9M, FY2024). Over the same period, payments to lease space and racks in other companies’ facilities climbed steadily: ₱28.7M (2018) → ₱177.3M (2021) → ₱192.0M (2023) → ₱362.3M (2024).

Building capacity did not reduce the rental bill in any year of the series. In FY2024, the year of the largest single build, DICT simultaneously held four separate colocation contracts with four different providers.

F3

Sixteen serial renewals of two colocation contracts, at a flat price

The Central Luzon and NCR2 colocation contracts with ePLDT, Inc. were each renewed eight times between 2021 and 2022 — sixteen renewal instruments worth ₱386.0M, or ₱419.0M counting the two original 2020 contracts. Twelve of the sixteen renewals carry one of exactly two amounts: ₱21,900,000.00 (Central Luzon, six times) or ₱21,800,000.00 (NCR2, six times).

The cadence is exactly four renewals per site per year, in both 2021 and 2022 — consistent with terms of roughly three months each. On that reading the Central Luzon requirement cost ₱87.6M a year by 2022, against ₱33.9M for the original 2020 contract. The list states no contract term, so the comparison cannot be closed.

A first extension is ordinary. An eighth renewal at an unchanged price, with no rebidding visible in the list, is the pattern that ought to draw attention — particularly where the incumbent also holds cloud and managed-services contracts with the same department.

F4

One corporate group holds a quarter of the programme

33 suppliers appear in the list. The top five hold 54.7% of value; the top ten hold 82.4%. Counting PLDT, Inc., ePLDT, Inc. and the Vitro / ePLDT joint venture together, the PLDT group accounts for ₱1.21B across 24 contracts — 24.2% of the eleven-year total, and the largest single relationship in the programme by a wide margin.

Radenta Technologies, Inc. appears in two separate joint ventures (with MaroonStudios and with Crayon Software Experts) holding ₱520.4M combined.

F5

₱2.46B of cloud subscriptions bought through at least six different intermediaries

Cloud subscription and managed services are now the largest category at ₱2.46B (49.3%) across just 12 contracts. They are spread across Amazon Web Services directly (₱186.8M), Google Cloud through MaroonStudios JV Radenta (₱379.7M), “public multicloud” through Crayon Software Experts in two lots (₱581.9M), private cloud through Multi-Core JV CloudSigma (₱325.4M), the e-Government Cloud through ePLDT (₱464.2M), and a data warehouse platform through MaroonStudios (₱17.4M).

Five of the twelve, worth ₱1.23B, are described as maintaining an existing environment. The list does not show how much committed capacity was actually consumed under any of them.

How the ₱2.46B of cloud was actually contracted

All twelve cloud contracts, showing who was paid and whether the platform named in the contract title is the party that received the money. The right-hand column reports only what the contract titles state — corporate reseller relationships are not recorded in the source document.

FYEntryContractContracting party (who is paid) PlatformAmount (₱)
2016#1Design, build & operate a complete cloud solutionVibal Group, Inc. + Philcox (Phils.), Inc. JVno platform named372,579,426.00
2020#11Cloud hosting for government agencies and projectsAmazon Web Services, Inc.contracting party is the platform21,257,711.17
2020#12Managed services, cloud environment of the Government Common PlatformMicro-D International, Inc.no platform named109,470,500.00
2022#31Data warehouse platform cloud hostingMaroonStudios, Inc.no platform named17,380,000.00
2022#32Subscription & maintenance, existing cloud infrastructure (AWS)Amazon Web Services, Inc.contracting party is the platform165,528,752.85
2023#41Subscription & maintenance, existing Google Cloud infrastructureMaroonStudios, Inc. JV Radenta Technologies, Inc.platform named, contractor is not it152,948,980.87
2023#42Existing public multicloud infrastructure — Lot ACrayon Software Experts Phils., Inc. JV Radenta Technologies, Inc.no platform named367,478,048.71
2023#43Existing public multicloud infrastructure — Lot BCrayon Software Experts Phils., Inc.no platform named214,474,808.72
2024#51Existing private cloud environment of the governmentMulti-Core Technology Resources Inc. JV with CLOUDSIGMA AGplatform inside the JV325,353,168.00
2024#54Managed services, the e-Government CloudePLDT, Inc.contractor’s own cloud464,188,000.00
2024#55Public cloud, pre-production environmentePLDT, Inc.contractor’s own cloud19,888,000.00
2025#65Subscription for the Google Cloud infrastructureMaroonStudios, Inc. JV Radenta Technologies, Inc.platform named, contractor is not it226,788,000.00
7.6%
Contracted directly with the platform owner — AWS, twice
₱186,786,464.02 · 2 contracts
92.4%
Contracted through a local company or joint venture
₱2,270,548,932.30 · 10 contracts
30.4%
Held by ventures including Radenta Technologies, across two different JV partners
₱747,215,029.58 · 3 contracts
49.9%
Contracts maintaining an “existing” environment
₱1,225,783,759.15 · 5 contracts

Three things follow. Google Cloud was never contracted from Google — ₱379.7M across two contracts, both through the same joint venture — while AWS, the only platform contracted directly, is the smallest hyperscaler line. Both lots of the FY2023 multicloud procurement went to the same principal company, Crayon, one with a JV partner and one without, totalling ₱582.0M; lotting normally exists to widen participation. And the reseller margin is invisible throughout: with no ABC and no consumption figures, nothing shows what share of ₱2.27B was platform capacity and what share was intermediary fee.

Note: “GCP” in entry 12 is the Government Common Platform, not Google Cloud Platform.

F6

The single largest contract is the Subic build, at ₱697.9M

“Development of the DICT Subic Data Center Site Facilities and Integrated Network Security Infrastructure” was awarded to DBP Data Center, Inc. in FY2024 — 14.0% of the entire eleven-year programme in one contract, and the only entry of its size. Related Subic entries are small by comparison: physical security (₱3.6M) and pest control and disinfection (₱179.0K).

The list records no completion status, milestone schedule, or commissioning date for the facility.

F7

The list includes items that are not data center infrastructure

Five entries totalling ₱1.20M sit oddly in a data center project list: office furniture for the DICT Central Office in two lots (₱167,000 and ₱108,900), multifunction printer inks (₱348,369), a hotel venue with meals for a stakeholders’ meeting (₱400,000), and pest control (₱178,990).

The amounts are immaterial. What they raise is a scoping question: if furniture and printer ink were counted as NGDC projects, the criteria used to assemble this list are not obvious, and it is not possible to confirm from the document that the list is complete.

F8

The submission itself has gaps that block price verification

Entry no. 70 does not exist — the numbering runs 69, then 71. The last three entries carry no Project ID at all. Project IDs are not chronological (ID 1352 is dated 2023 while 1353 and 1354 are dated 2022), and one is formatted differently (1553-C).

More consequentially, the list has no column for approved budget for the contract, procurement modality, award date, contract duration, number of bidders, or delivery status. Without the first two, no judgement about whether any of these ₱4.98B in contracts was competitively priced can be made from this document.

F9

Eleven years of data center spending, with no procurement of compute

Searching all 72 entries for servers, storage or compute returns nothing. This is the complete list of entries that touch hardware in any form:

FYEntryWhat it boughtAmount (₱)
2017#4 Oracle — support services on software and hardware products 34,928,030.94
2019#9 Oracle — extension of the same support4,324,172.80
2022#30 Anti-DDoS protection license15,497,000.00
2024#57 Network appliances, GDC1 upgrade1,463,100.00
2024#59 Desktop computers — monitoring workstations for GDC1 and GDC3 819,000.00

₱57.0M, or 1.1% of the programme — and the only actual machines in it are desktops for staff to watch the data centers with. Every large line in this list is either a place to put machines (₱888M of buildings and power) or someone else’s machines (₱2.46B of cloud). Nothing in between.

That leaves a contradiction. Colocation is worth buying only if you own hardware that needs housing — nobody rents racks to hold a cloud subscription. So ₱1.29B of leased rack space implies a substantial government-owned estate that this list never shows being bought. And if the answer is that workloads moved to cloud, colocation should be shrinking; instead it went from ₱192.0M (FY2023) to ₱362.3M (FY2024). Even “Government Data Center 2” turns out to be leased space, across four contracts with two providers.

The likeliest explanation is scope rather than absence: the original compute was probably procured before FY2016, under the predecessor ICT office, and simply falls outside this submission. The 2017 Oracle contract supports that — no agency pays ₱34.9M to support hardware it does not already own. But that reading raises its own problem, because enterprise hardware runs five to seven years and no refresh appears anywhere in this list. Either it was procured outside this submission, or it has not happened.

The same gap applies to the FY2024 Subic build. ₱697.9M developed the site; no compute was procured to fill it. A facility with power and cooling and no servers is a shell, so the cost of making Subic operational is still ahead — which bears directly on the budget now before the Committee.


The renewal chain

Two colocation requirements, renewed sixteen times between them. Each block is a separate contract instrument recorded in the DICT list.

Supplier concentration

Top ten suppliers by total contract value, out of 33. Entities in the PLDT group are marked separately; together they hold ₱1.21B, or 24.2% of the programme.

Contract value by supplier, FY2016–FY2026

Hover a bar for the contract count.

  • PLDT group (PLDT, ePLDT, Vitro JV)
  • All other suppliers

The full ledger

All 72 entries as reported. Filter by year or category, or search supplier and project names.

No.Proj IDFYProjectSupplier Contract (₱)

Source and method

  • Figures are transcribed from photographs of the five-page DICT list and were read back against magnified crops of the amount column; every amount in this brief matches the source document.
  • Amounts are final contract values as reported by DICT, not obligations or disbursements. They are not adjusted for inflation and do not represent cash actually paid.
  • Category assignments are analytical, applied here for grouping; the source document has no category column. The FY2016 Vibal / Philcox design-build-operate consultancy is grouped with cloud because that is what it procured.
  • “PLDT group” aggregates PLDT, Inc., ePLDT, Inc. and the Vitro, Inc. / ePLDT joint venture as named in the list. No corporate registry check was performed.
  • The source document includes a Google Drive link per entry. Those URLs were not transcribed: the photograph resolution makes character-level transcription of the folder IDs unreliable.
  • Findings are observations about the document and the pattern of spending. None asserts irregularity.