These are proposals, not yet final. The NEP is the President's proposal and House Bill No. 10858 the House's. The Senate and the bicameral conference can still change the bill, and it is not law until the 2027 General Appropriations Act is signed.
FY2027 budget · Department of Public Works and Highways

The House kept DPWH's budget almost level, and rewrote what it pays for

The President proposed ₱642.6 billion for the Department of Public Works and Highways in 2027. The House of Representatives passed ₱654.1 billion — a rise of ₱11.5 billion, or under 2%. The total barely moved; what the money pays for was rewritten. We compared the two budgets, the President's proposed National Expenditure Program (NEP) and House Bill No. 10858, line by line.

+₱11.5BDPWH total: ₱642.6B proposed, ₱654.1B in the House bill
−₱73.0Bcut from loan-funded projects (₱117.8B to ₱44.8B)
+₱72.5Badded to the Basic Infrastructure Program (₱148.5B to ₱221.0B)
6,212new projects worth ₱180.5B that are not in the NEP

How much of the budget the House changed

MeasureAmountShare of DPWH
Total DPWH budget in the House bill₱654.1B—
Change from the NEP (₱642.6B)+₱11.5B+1.8%
Moved from large loan-funded projects into local projects≈₱73B≈11%
All money that changed office (rises plus cuts)≈₱98B≈15%

The first two rows say the department stayed almost the same size. The last two say how much of it was rewritten: roughly an eighth of DPWH's budget was taken from a few big foreign-assisted projects and spent instead on thousands of smaller local projects, most of them lodged with district engineering offices.

Where the money came from

Salaries were left unchanged. The change sits in infrastructure spending, and the largest cuts were to foreign-loan projects:

Laguna Lakeshore Road Network−₱27.0B
Bataan–Cavite Interlink Bridge−₱14.0B
Cebu–Mactan 4th Bridge−₱6.0B
Pasig–Marikina River Channel−₱5.5B
Davao City Bypass (two packages)−₱5.5B

How the numbers fit together

The House added to some programme lines and cut others. The additions and the cuts are each far larger than the net change: they nearly cancel, leaving a ₱11.5B increase in the total DPWH budget.

Change, House vs. NEP₱B
Additions
BIP: multi-purpose buildings+42.73
BIP: access roads and bridges+29.27
All other additions (flood control, road upkeep, water supply and the rest)+26.91
Total additions+98.91
Cuts
Laguna Lakeshore Road Network−27.00
Bataan–Cavite Interlink Bridge−14.00
Cebu–Mactan 4th Bridge−6.00
Pasig–Marikina River Channel−5.50
Davao City Bypass (two packages)−5.50
All other cuts−29.42
Total cuts−87.42
Net change in the DPWH budget+11.49

So the ₱73B cut from foreign-assisted projects was recycled almost entirely into the Basic Infrastructure Program (+₱72.6B): a swap, not new money. The department's net ₱11.5B growth comes from the rest — chiefly road upkeep and the flood programme, less about ₱2.7B taken out of Support to Operations.

See every addition and cut, line by line →

District engineering offices gained ₱53.9B overall (₱129.6B to ₱183.6B): 158 offices gained, 20 lost, 20 were unchanged. The DPWH Central Office fell by ₱42.4B.

How many projects the House changed

The House bill lists 16,270 DPWH projects; the NEP proposed 11,303. By count the House's intervention is far larger than the money suggests — more than a third of the projects in the House bill are ones the proposal did not have.

OutcomeProjectsShare
New in the House bill (no NEP match)6,21238% of the House's list
Carried over unchanged9,66959%
Carried over, amount changed3892%
In the NEP, not found in the House bill1,0109% of the NEP's list
Needs review (ambiguous)235—

In all the House touched 7,611 projects — 6,212 new, 389 re-priced and 1,010 dropped. That is the opposite story from the money: the total rose under 2%, but the House rewrote more than a third of the project list, mostly by adding thousands of small local projects (median ₱10 million) in place of a few large loan-funded ones.

Thousands of new projects

Those 6,212 new projects are worth up to ₱180.5B, but that is not money added to the budget. The House also dropped ₱57.0B of NEP projects and cut ₱82.9B from projects it kept — mostly the loan-funded flagships (Laguna Lakeshore −₱27.0B, Bataan–Cavite −₱14.0B, Cebu–Mactan −₱6.0B). It largely swapped the project list: the net movement at project level is roughly +₱40B, and the department as a whole rose only ₱11.5B.

District offices with the largest increases

District engineering officeLegislative district(s)ProposedHouseChange
Ilocos Norte 1stIlocos Norte 1st₱0.41B₱4.79B+₱4.38B
Davao de Oro 1stDavao de Oro 2nd₱0.66B₱2.35B+₱1.68B
Misamis Occidental 2ndMisamis Occidental 2nd₱0.20B₱1.85B+₱1.65B
South Cotabato 2ndSouth Cotabato 2nd and 3rd₱0.50B₱2.08B+₱1.58B
Isabela 4thIsabela 4th and 6th₱1.58B₱3.10B+₱1.52B

Amounts are each office's total appropriation. They do not include Central Office projects built in the same area.

District offices: the ten largest and ten smallest

All 198 district engineering offices, ranked by their total appropriation in the House bill. Each figure is the office's own appropriation; it does not include Central Office projects built in the same area. "Proposed" is the NEP, "House" is HB 10858.

Ten largest

District engineering officeLegislative district(s)ProposedHouseChange
Ilocos Norte 1stIlocos Norte 1st₱0.41B₱4.79B+₱4.38B
Nueva Ecija 1stNueva Ecija 1st and 2nd₱2.83B₱3.91B+₱1.07B
Bulacan 2ndBulacan 4th; Bulacan 6th; City of San Jose del Monte (lone)₱3.45B₱3.50B+₱0.05B
Isabela 4thIsabela 4th and 6th₱1.58B₱3.10B+₱1.52B
Metro Manila 3rdCaloocan City 1st, 2nd and 3rd; Valenzuela City 1st and 2nd₱2.89B₱2.99B+₱0.09B
Batangas 2ndBatangas 2nd and 5th₱1.75B₱2.94B+₱1.19B
Bulacan 1stBulacan 1st, 2nd and 5th₱2.35B₱2.66B+₱0.31B
Cavite 1stCavite 1st, 3rd, 6th and 7th₱1.79B₱2.63B+₱0.85B
Isabela 3rdIsabela 2nd and 3rd₱1.53B₱2.52B+₱0.99B
Isabela 1stIsabela 1st₱1.33B₱2.41B+₱1.08B

Ten smallest

District engineering officeLegislative district(s)ProposedHouseChange
Davao City 3rdDavao City 2nd₱0.04B₱0.04B—
Davao CityDavao City 1st₱0.04B₱0.04B—
Southern Leyte 2ndSouthern Leyte 2nd₱0.05B₱0.05B—
Agusan del Sur 1stAgusan del Sur 1st₱0.09B₱0.06B−₱0.03B
Isabela CityBasilan (lone)₱0.07B₱0.07B—
Southern Leyte 1stSouthern Leyte 1st₱0.17B₱0.09B−₱0.08B
Ilocos Sur 1stIlocos Sur 1st₱0.10B₱0.10B—
Bukidnon 3rdBukidnon 1st₱0.07B₱0.10B+₱0.03B
Leyte 1stLeyte 1st₱0.10B₱0.10B—
Agusan del NorteAgusan del Norte (lone)₱0.13B₱0.13B—

About these figures

Sources: FY2027 National Expenditure Program, Volume II-B, and House Bill No. 10858 (DPWH section and Volume I-C). Totals match each document's printed totals to the peso.

"New" means a project in the House bill with no counterpart in the NEP. Neither document shows who requested a project.

The proposal is a scanned document. Project names were matched by computer and checked against printed totals. A small share of matches may be imperfect; office totals are not affected.

A full itemized record of the ₱11.49 B DPWH amendment from the House BARSc hearing is in the BARSC 2027 record.